Lisa Grady of Bridge Housing to RWQCB: "We want protection from liability after we buy Marinwood Plaza"

History of Marinwood Plaza in 2014


Renee Silveira was shocked to learn that Bridge Housing wants a guarantee after purchasing Marinwood Plaza that they will not be liable for the toxic waste.* It seems no one wants to be the responsible party to clean up all of the residual toxins that could find its way to the Silveira Ranch water source, poisoning the dairy herd, the residents and potentially thousands of people that drink milk.  

Supervisor Susan Adams called multiple times and Assemblymen Mark Levine called on behalf of the developers and landowners to vacate the toxic waste clean up order and extend the final clean up date  so they may have additional time to get financing and permits.  

Why didn't they consider the risks to PUBLIC HEALTH first?  
Lisa Grady, Marinwood Village, Former Senior Project Manager

See full Board Packet with the Geologica Report responses from Marinwood Plaza, LLC, Bridge Housing and Silveira Ranches HERE

Email sent to the RWQCB on January 8, 2014.


------------------------------------------------------------------------------------------------------
From: Lisa Grady
To: Aue, Kent@Waterboards
Cc: Tom Graf (tom@grafcon.us)
Subject: Water Board Order Regarding the Marinwood Plaza site
Date: Wednesday, January 08, 2014 4:47:12 PM

Kent:

As you know, BRIDGE intends to develop the site post-remediation and we have assumed
that vapor mitigation in the form of sub-slab ventilation or ventilated flooring will be
necessary for some period of time in the areas currently showing vapors exceeding
allowable concentrations. We want to make sure this is taken into account with regard to
the order.

Additionally, without understanding the constraints and regulations governing the
Waterboard, it would be ideal if staff were able to modify the order with regard to timing.
While we hope this won’t be the case, the entitlements and environmental approvals may be litigated. We were anticipating that the completion of the soil removal would occur once BRIDGE has secured the necessary financing to begin construction. We anticipate that the entitlement and environmental approvals will be secured in 12 to 18 months from today. Once that occurs, and assuming there is no litigation, we would proceed with the completion of the construction documents, financing and building permitting. Typically, that takes about a year’s time. So, the earliest construction start date isn’t likely to be until June of 2016.

The other item I would like to discuss at some point is the Prospective Purchaser document
we need to protect us from liability once we take title. You indicated that the Water Board
no longer issues these but I’d like to understand how we get to an equivalent level of
protection absent that document.

Please give me a call if you have questions. Thanks and Happy New Year.

Lisa

Lisa Grady | Senior Project Manager
BRIDGE Housing Corporation | 345 Spear Street, Suite 700, San Francisco, Ca., 94105
Direct: 415.321.3534
p. 415.989.1111 ext 7514
f. 415.495.4898

lgrady@bridgehousing.com

Pregnant women and children are particularly vulnerable to toxins in the environment.
*Of course, if anyone were to receive such a guarantee, then the public will never be certain that a full cleanup has taken place.  It simply gives the buyer a permanent "get out of jail card" free.

Postscript:  Lisa Grady left employment with Bridge Housing shortly after this letter was discovered and made public.