Marinwood CSD 5/11/2021 Marinwood CSD approves MOST EXPENSIVE MAINTENANCE SHED in Marin County history!
Tuesday, May 11, 2021
Secret Architect hired in Feb 2018 for $12,000 all inclusive price.
Marinwood CSD general manager Eric Dreikosen reports hiring an architect for $12,000 for all inclusive price for a maintenance shed proposal but fails to reveal that it is former Marinwood CSD director, Bill Hansell . Dreikosen was hired by the CSD board that included Bill Hansell in 2015 . The total budget cost of the project has not been revealed and the architects fees have exceeded the $12,000 before reaching site plan approval stage. Another architect with decades of experience with public works projects, bid $13,800 for the ENTIRE PROJECT including site plan review (fixed price $2800), construction oversight and architects fee of 8% based on $100,000 construction cost. He lost the bid. The CSD has attacked critics as spreading "misinformation" yet hides its plans and budgets. You be the judge how well they handle the public's business. This clip is from the February 13, 2018 Marinwood CSD board meeting.
"Public Outreach?" asks Planner. Jeff Naylor shuts down discussion in 2018.
At the Jan 27, 2020 Marin Planning Commission meeting, commissioner asks about the public outreach. Jeff Naylor's famous response in September 2018 to a petition of 200 residents tells the real story of "public outreach" Still there has been no meeting. The project budget is secret and the architect, a former CSD politician has estimated billing 500% of the initial estimates BEFORE the plan has been approved. Hansell Design has a highly unusual "unlimited billing" fee arrangement with NO PERFORMANCE provisions. While CSD Director, Bill Hansell hired current manager Eric Dreikosen at double his previous compensation despite NO EXPERIENCE in managing a CSD. This is small town corruption on display enabled by the entire CSD board.
The Multimillion Dollar Shed is Missing Area for Loading/Unloading Landscaping Materials and Vehicle Movement.
The proposed Marinwood Maintenance Compound won't have a grassy area in front. This area must be used for loading/unloading of landscape materials. |
The Marinwood CSD maintenance crew generates big piles of landscaping debris and trash each week. They store this in the large open area next to the horse shoe pits in Marinwood Park to allow the convenient loading/dumping of material.
![]() |
| Large piles of landscaping waste and trash is stored in the open at the Maintenance shed |
A bucket loading operation requires much space as you can see in this video. Generally, the dump trailer is loaded from the side into the center of the trailer. The operator must do this to balance the load for safety. This means the bucket loader requires a large area for scooping material and turning.
The truck and trailer must be parked perpendicular to the bucket loader.
In the site plan of the proposed Maintenance Facility below, you can see that the only area where this operation can take place is IN FRONT of the Maintenance Facility. The architect has drawn a walking path in this area to deceive the planning department. There is NO ROOM inside the walled maintenance compound to perform a mechanized loading operation.
Our Ford F250 is 22 feet long.and the dump trailer is approximately 20 feet long including tongue.
This means that 42 feet of space will be required for the truck/trailer and an additional 40' to 60' feet to the side will be required for the bucket loader and material. This will occupy all the area between the maintenance building and Miller Creek.
| Proposed Maintenance Facility with old facility overlay in brown |
This drawing shows the footprint of the proposed Maintenance Bldg and the old building footprint in brown. The brown box on the left is the area the architect calls open storage. In fact the entire area from the current building to the horse shoe pit is used for landscaping debris, parking and tool storage. Clearly there is no area suitable for loading and unloading material within the proposed Maintenance Building above. The architect shows this area as green space and a walking path but it will not happen. It will be used for parking and storage of debris and landscaping materials. The is no alternative. What happened to the access road that the architect showed in previous drawings? It has disappeared. This is highly deceptive. The architect must show where essential activities will take place on the building site. Safety vehicles and pedestrians must pass through this area. The drawings do not show the true impact to the stream conservation area and Marinwood Park. The proposed Marinwood CSD Maintenance Facility is simply too big and inefficient, harms the environment and occupies land that should be used for recreational purposes as intended. |
The Multi Million Dollar Maintenance Shed won't allow our Vehicles to Turn Around
The Marinwood Drive Through Maintenance facility is a bust

| Option #3 is the "environmentally preferred" option for our next maintenance facility. |
Monday, May 10, 2021
Friday, May 7, 2021
Wednesday, May 5, 2021
Wednesday, April 28, 2021
Marinwood Maintenance Shed Bidder involved in Major Bribery Scandal
A quick investigation of the construction bidders for the Marinwood Maintenance Shed found that Azul Construction was involved in a major bribery scandal in the City of San Francisco. The U.S. Attorney charged its chief executive with bribery and faces up to 10 years in prison.
See the story HERE
Tuesday, April 27, 2021
Marinwood CSD Million Dollar Maintenance Shed-Bid Opening 4/27/2021
- Murray Building, Inc., Santa Rosa: $1,059,000
- M3 Integrated Solutions, Inc., Santa Rosa: $1,072,000
- CF Contracting, Inc., San Francisco: $1,169,425
- CWS Construction Group, Inc., Novato: $1,287,000
- Azul Works, Inc., San Francisco: $1,297,000 see article about corruption allegations HERE
Monday, April 19, 2021
Last Minute Legal Notice for Contractor Proposals for Marinwood Maintenance Shed.
NOTICE TO CONTRACTORS INVITING SEALED PROPOSALS OF BIDS NOTICE IS HEREBY GIVEN that the Marinwood Community Services District will accept sealed bids for its Park Maintenance Facility project at 775 Miller Creek Road, San Rafael, CA 94903 by or before 2:00PM, Tuesday, 04/27/2021. Any proposals received after this time will not be opened and will be returned. Timely received proposals will be collected by District staff at 2:00 PM and will be opened and read thereafter via Zoom webcast. The Scope of Work is described as follows: Furnishing all required labor, materials, transportation, equipment, incidentals, and services for construction of a new Park Maintenance Facility consisting of a 1,200sf enclosed workshop, break room (not incl cabinetry and sink re: Add Alt 02 below), restroom, and storage closet contiguous with a 1,300sf covered (unconditioned) storage area. In addition, there are three (3) Additive Alternate (Add Alt) Bid Items, as follows: Add Alt 01: East & West Courtyards totaling 1,960sf, including fencing on concrete stem walls, rolling gates, and compacted gravel surfaces. Add Alt 02: Break Room cabinetry with sink Add Alt 03: Vertical Shade and Security Fins at openings above wall on column line 03 between lines A.2 and C.2 to be detailed in a separate Addendum Work shall be done in accordance with official plans and specifications available for printing by online order at Contractor's expense from NorthBay Reprographics, 4314 Redwood Highway, Suite 200, San Rafael, CA 94903, https://northbayrepro.com , Tel: 415-491-1112, Email: prints@northbayrepro.com . Electronic copies of all documents, including the complete Bid Packet, are available for download from the Marinwood CSD's website at: https://www.marinwood.org/contracts-rfp Partial sets of Bid Documents are not available from the Owner or Architect. Contractors shall perform a mandatory site visit at the Contractor's convenience and submit the Verification of Site Visit form included in the Bid Packet with their bid. Site Visit form must be signed off by the District Manager or Project Architect. Award of contract, if awarded, will be to the responsible bidder with the lowest responsive bid whose proposal complies with prescribed requirements, and will be within sixty (60) days after receipt of proposals. The Marinwood Community Services District reserves the right to reject any or all bids and the right to waive any irregularities. The provisions of Public Contract Code 22300, regarding substitution of securities for monies withheld to ensure performance shall apply to this contract. All Bidders shall be licensed under the provisions of Chapter 9, Division 3, of the Business and Professions Code of the State of California to do the type of work contemplated in the project and shall be skilled and regularly engaged in the general class or type of work called for under the Contract Pursuant to Labor Code Section 1771.1 and subject to exceptions set forth by that section, no contractor or subcontractor may be listed on a bid proposal unless registered with the Department of Industrial Relations pursuant to Labor Code Section 1725.5, and no bid shall be accepted nor contract or subcontract be entered into without proof of the contractor's or subcontractor's current registration to perform public work pursuant to Labor Code Section 1725.5. Any work performed on the project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contractor is required to submit all certified payroll records directly to the Department of Industrial Relations in electronic format. Any bidder or contractor not properly licensed with the State of California shall be subject to all legal penalties imposed by law, including, but not limited to, any appropriate disciplinary action by the Contractors' State License Board. Failure of the bidder to obtain proper and adequate licensing for an award of the contract shall constitute a failure to execute the contract and shall result in the forfeiture of the security of the bidder. Bids are required for the entire work described herein. This contract is subject to state contract nondiscrimination and compliance requirements pursuant to Government Code, Section 12990. The successful bidder shall furnish a payment bond and a performance bond. Pursuant to Section 1773 of the Labor Code, the general prevailing wage rates for Marin County where the work is to be done have been determined by the Director of the California Department of Industrial Relations. These wages are set forth in the General Prevailing Wage Rates for this project, available at the Department of Public Works, and are also available at the State of California Division of Labor Statistics and research web site at www.dir.ca.gov/dlsr/pwd/northern.html April 15, 2021